Review Kemajuan Tambang Bulan November 2019 Dan Perencanaan Tambang Bulan Desember 2019 Di Tambang Terbuka Batubara

Authors

  • Sari Melati
  • Abdul Hakim Program Studi Teknik Pertambangan, Fakultas Teknik, Universitas Lambung Mangkurat, Indonesia
  • Marselinus Untung Dwiatmoko Program Studi Teknik Pertambangan, Fakultas Teknik, Universitas Lambung Mangkurat, Indonesia

DOI:

https://doi.org/10.33536/jg.v8i03.1405

Keywords:

mine design, mine planning, short-term planning, coal mining, open pit mining

Abstract

Monthly planning, based on time period, is included in short-term planning. The work phase that plays an important role for effective and efficient mining operations in monthly planning is evaluating the progress of the previous month's mine and planning the next month's mining stage. This research was conducted in an open-pit coal mine with the aim of describing a review of mine progress in November 2019 and planning for mining in December 2019. The mining plan includes the determination of the mine boundary, pit progress design, disposal progress, mine hauling road, mining stages, production schedule, and the number of loading hauling and suppor equipment,. Minescape 5.7 software was used in the mine design process and calculation of overburden and coal volumes. The pit limit was determined from the monthly target and the mine design did not exceed the annual design. The number of tools plan takes into account the productivity of available mechanical devices in order to reach monthly targets. The results of the review in November 2019, actual overburden and coal were excavated more than 10% of the target. The pit topography at the end of the month was less than the request level (undercut). Actual horizontal distance and vertical distance in coal getting were according to plan. Whereas in overburden removal, horizontal distance was 11% more than the plan and vertical distance was 7% less than the plan. The planned mine progress in December 2019 uses stripping ratio numbers 3, the area of the bottom pit area is 21.48 Ha with RL -64 and -48, the area of the Low Wall area is 16.72 Ha with RL -16. Coal production in December 2019 is planned to be 400,000 tons, with overburden removal of 1,200,000 bcm. Targets will be achieved with 4 units loading equipment and 96 units hauling equipment for overburden removal and 1 loading equipment and 17 units hauling equipment for coal getting, 3 units dozers in the pit and 2 units dozer at disposal.

Downloads

Download data is not yet available.

References

Aryanda, D., Ramli, M., & Djamaluddin, H. 2016. Perancangan Sequence Penambangan Batubara Untuk Memenuhi Target Produksi Bulanan. Jurnal Penelitian Geosains, 10(2).

Firdaus, S. A., Nurhakim, N., Saismana, U., & Nor, T. 2017. Perencanaan Tahapan Penambangan Bulanan Pada Tambang Terbuka Batubara Metode Open Pit. Jurnal Geosapta, 2(1).

Ibrahim, E. 2015. Rekonsiliasi Penambangan Antara Rencana Penambangan Bulanan dengan Realisasi di Tambang Swakelola B2 PT. Bukit Asam (Persero), Tbk. Jurnal Ilmu Teknik, 3(1).

Jailani, A., Triantoro, A., & Hakim, R. N. 2018. Perencanaan Tambang Pada Lokasi Pit East Dan Pit West Di Pt Wings Sejati Jobsite PT Bangun Nusantara Jaya Makmur. Jurnal Geosapta, 4(2).

Leite & R. Dimitrakopoulos. 2007. Stochastic optimisation model for open pit mine planning: application and risk analysis at copper deposit. Mining Technology, 116:3, 109-118, DOI: 10.1179/174328607X228848

Mai, N. L., Topalt, E., & Ertent, O. 2018. A new open-pit mine planning optimization method using block aggregation and integer programming. Journal of the Southern African Institute of Mining and Metallurgy, 118(7), 705-714.

Michelle Blom, Adrian R. Pearce & Peter J. Stuckey. 2017. Short-term scheduling of an open pit mine with multiple objectives. Engineering Optimization. 49:5, 777-795, DOI: 10.1080/0305215X.2016.1218002

Misradin, M., Santoso, E., & Melati, S. 2020. Perencanaan Penambangan Batubara Pada Pit B Selama Triwulan I Tahun 2019 Di PT Kalimantan Lintas Khatulistiwa. Jurnal Himasapta, 5(1).

Morales, N., Seguel, S., Cáceres, A., Jélvez, E., & Alarcón, M. 2019. Incorporation of geometallurgical attributes and geological uncertainty into long term open pit mine planning. Minerals, 9(2), 108.

Otto, T. J., & Musingwini, C. 2019. A spatial mine to plan compliance approach to improve alignment of short-and long-term mine planning at open pit mines. Journal of the Southern African Institute of Mining and Metallurgy, 119(3), 253-259.

Paithankar, A., & Chatterjee, S. 2019. Open pit mine production schedule optimization using a hybrid of maximum-flow and genetic algorithms. Applied Soft Computing, 81, 105507.

Pratama, R. A., Saismana, U., Riswan, R., & Irawan, H. 2019. Perencanaan Sequence Bulanan Tambang Batubara di PT Batubara Kalimantan. Jurnal Himasapta, 3(01).

Rahmanpour, M., & Osanloo, M. 2016. Determination of value at risk for long-term production planning in open pit mines in the presence of price uncertainty. Journal of the Southern African Institute of Mining and Metallurgy, 116(3), 229-236.

Suhairi, R., Nurhakim, N., & Riswan, R. 2018. Evaluasi Kemajuan Tambang Bulanan Berdasarkan Metode Survey Pada PT XYZ. Jurnal Geosapta, 4(01).

Downloads

Published

31-12-2020

How to Cite

Review Kemajuan Tambang Bulan November 2019 Dan Perencanaan Tambang Bulan Desember 2019 Di Tambang Terbuka Batubara. (2020). Jurnal Geomine, 8(03), 181-192. https://doi.org/10.33536/jg.v8i03.1405

Similar Articles

1-10 of 115

You may also start an advanced similarity search for this article.