Rancangan Penambangan Jangka Pendek Pada Pit Utara di PT Tubindo Kabupaten Bulungan Provinsi Kalimantan Utara

Authors

  • Habibie Anwar
  • Rafly Esa Mahendra Program Studi Teknik Pertambangan, Universitas Muslim Indonesia, Makassar, Indonesia
  • Hasbi Bakri Program Studi Teknik Pertambangan, Universitas Muslim Indonesia, Makassar, Indonesia
  • Anshariah Program Studi Teknik Pertambangan, Universitas Muslim Indonesia, Makassar, Indonesia
  • Alam Budiman Thamsi Program Studi Teknik Pertambangan, Universitas Muslim Indonesia, Makassar, Indonesia
  • Nur Asmiani Program Studi Teknik Pertambangan, Universitas Muslim Indonesia, Makassar, Indonesia
  • Ardiawa Site Manager dan Head Departemen Engineering, PT Tubindo, Indonesia
  • Romi Site Manager dan Head Departemen Engineering, PT Tubindo, Indonesia

DOI:

https://doi.org/10.33096/geomine.v11i1.142

Keywords:

Mine planning; short-term; coal; overburden; stripping ratio; sequence

Abstract

Short-term mining design is an important part of mine design in mining activities to achieve production targets and provide predictions about the concept of mining progress over a certain period. Therefore, a short-term mining concept must be created. The short-term mining plan is divided into 4 months starting in May, June, July, and August.  In these mining activities, the company limits the stripping ratio not to exceed 7: 1. The parameter used as an evaluation of the determination of the design obtained is volume.  The results are designed based on the optimization pit design with an overburden seam A volume of 7,507,061.77 BCM, coal of 1,373,043.20  tons with a cumulative stripping ratio of 5.4: 1. The design made for the  North Pit mining sequence design in  May received an overburden of 358,884.62 BCM and coal of 138,944.67 tons with a stripping ratio of  2.6:1, in June overburden of   406,408.82 BCM and coal of 120,612.66     tons with stripping ratio 3.4: 1, month juli overburden  287,681.75  BCM and coal 136,266.90 tons with stripping ratio 2.1: 1, August overburden 520,148.44  BCM and coal 144,308.96 tons with stripping ratio   3.6   :1 with an area to be mined reaching 15.5 Ha

Downloads

Download data is not yet available.

Downloads

Published

17-07-2023

How to Cite

Rancangan Penambangan Jangka Pendek Pada Pit Utara di PT Tubindo Kabupaten Bulungan Provinsi Kalimantan Utara. (2023). Jurnal Geomine, 11(01), 102-110. https://doi.org/10.33096/geomine.v11i1.142

Similar Articles

1-10 of 98

You may also start an advanced similarity search for this article.