THE ANALYSIS OF WASTE ACTIVITIES IN SUPRAMAK BED PRODUCTION BY USINGVALUE STREAM MAPPING AND VALSAT APPROACHES
Keywords:
waste analysis, lean manufacturing, Value Stream Analysis Tools, Value Stream MappingAbstract
X Ltd. is a company which is producing hospital equipment with one of its products
is supramak bed (patient’s bed). From the observation at the production floor of X
Ltd, several non-value added activities are identified, which are components
accumulation, reworking a number of products which do not meet the standards, idling
operators, and waiting in working process. Based on the results of VSM Current State
Map is obtained that total time for value added activities are 96816 seconds and for
non-value added activities are 80869 seconds. Based on WAM analysis, the highest
waste occurs during waiting time with an index of 19.09%. Based on VALSAT analysis,
the proposed input from researchers are as follows: giving the mandates to the
warehouse department, monitoring product flow, creating and enforcing SOP,
increasing the number of forklifts, and analyzing transportation effectiveness.